<>

Crumb Rubber Modifier in Asphalt Pavement

Chapter 4


Construction Process/Costs



Shipping

    Although the construction procedures used by the various agencies are similar, there are distinct differences. This chapter discusses the procedures used in terms of handling the CRM, the construction process, including plant operations, placement, and compaction. The costs for the asphalt-rubber binders and asphalt-rubber-modified HMA mixes are summarized.

    Shipping, Storage, and Handling of CRM Materials

    The CRM is produced using one of the following processes or combination of processes: ambient grinding, ambient granulating, cryogenic grinding, or wet grinding. The feed stock may be buffings, whole truck or automobile tires and, in one case, reject tennis balls. The key for the contractor or agency purchasing the material is that it meets the specifications, be uniform, be free of metal, contain very little fiber, and be relatively dry. Uniformity is required because if the gradation or chemical makeup of the rubber changes, it may change the properties of the resultant asphalt-rubber binder, such as viscosity, softening point, reaction time, etc. The material must be free of metal particles because they can, and have, damaged the contractor's pumping equipment. An excessive amount of fibers may cause nozzles to clog. The material is shipped to the asphalt-rubber blending operations in either 453-kg to 907-kg (997-lb to 1,995-lb) gaylord boxes, supersacks (approximately 1 metric ton [2,200 lbs]), bulk tanker trucks (similar to cement or lime bulk trucks), or in bags weighing 11 kg to 27 kg (24 lb to 59 lb). Figure 4 shows the supersack storage area on a project in California. After shipment to the project site, the rubber must be kept dry because moisture in the rubber can cause foaming of the asphalt cement. Once the material is at the project site, it can be loaded directly into a crumb rubber hopper on the blending equipment or it can be blown from the bulk tanker truck into a silo from which it can be augured into the asphalt-rubber blending unit. There have been reported problems with the material clumping in the large containers such as the gaylord boxes or super-sacks. Some rubber suppliers (generally at the request of the asphalt-rubber blender) have added up to 2 to 4 percent calcium carbonate or talc to the CRM to prevent the CRM from sticking together and thus to improve its free flow characteristics.

Construction Process: Blending

    The asphalt cement and the CRM are blended into a homogeneous asphalt-rubber system, which is reacted at elevated temperatures. Since the expiration of the patents on the asphalt-rubber process, there have been a number of different processes developed for blending the asphalt cement and the CRM. The time required to disperse, blend and react, or melt the CRM into the asphalt cement is dependent on a number of factors in the chemistry of the asphalt cement and CRM, as well as the particle size and texture of the rubber and the temperature of the blended material. The finer the material, the quicker it will "react." Basically, for a given weight of CRM, the reaction time is directly proportional to the diameter squared of the CRM particles. Also, the reaction time is inversely proportional to the temperature of the material. The reaction time will double with every 10°C (18°F) decrease in asphalt-cement temperature.(12) Adding CRM to the asphalt drops the temperature of the asphalt cement due to the ambient temperature of the CRM. For example, the addition of 20 percent CRM material to an asphalt cement at about 204°C (400°F) will cause the combined temperature to drop to about 177°C (350°F).

    The following paragraphs describe a multitude of blending systems that are now being used. Systems in use that were in the early stages of development or systems for which information was not available to the team are not discussed. Any system used for blending asphalt rubber should be evaluated for its ability to produce a uniform, fully "reacted" product.

    Arizona

      The CRM-HMA pavements built in Arizona require 17 to 23 percent of a 600 -181-m (30 mesh) CRM, and the specifications call for 30 to 60 minutes' reaction time after the rubber is blended with the asphalt cement. Therefore, the equipment consists of a mixing chamber and a reaction vessel to hold the material.

      FNF Construction in Tempe uses a CRM blending system manufactured by CE Enterprises in Albuquerque, New Mexico. The system consists of a portable asphalt-rubber mixing system and an agitation tank that is mounted on a trailer. It uses a mass flow asphalt-cement meter and a crumb rubber hopper that is equipped with a load cell. The load cell provides feedback to the computer to control the flow rate for the crumb rubber. The system is computer controlled to provide precise batch ratios. The computer also provides constant monitoring. The mixing tank is 1,135 liters (300 gallons) and is equipped with a twin-bladed shaft driven by a 3-hp vertical mixer. One mixing blade is positioned at the bottom, and the other blade is at the middle of the unit. The asphalt cement is introduced at 204°C (400°F). During the blending process the temperature of the blended material will drop to approximately 177°C (350°F). After the material is blended it is fed into a double-compartment, hot-oil-heated tank. The tank has a 56,781-liter (15,000-gallon) capacity, and each compartment is 28,390 liters (7,500 gallons). A turbine mixer is located in each compartment to keep the crumb rubber in suspension. Each tank compartment is equipped with independent heat coils. The asphalt rubber blend is held in the agitation tank for 45 minutes to an hour prior to use. This system can produce approximately 25 metric tons (28 tons) of asphalt-rubber binder per hour, or sufficient binder to allow a contractor to produce approximately 357 metric tons (400 tons) of rubber-modified HMA per hour.

      International Surfacing Incorporated (ISI) in Chandler uses a blending system that they developed based on the original McDonald process. (See figure 5 on page 4-4 for a schematic of the system.) With the ISI system, the asphalt cement and CRM are combined and mixed together in a blender unit and pumped into an agitated storage/reaction tank, where it is reacted for 30 to 60 minutes. It is a batch process. The amount of CRM is determined by weight for each batch. The temperature of the asphalt cement at the time the CRM is added should be between 190°C (375°F) and 232°C (450°F). This allows for the temperature drop caused by adding the ambient temperature rubber. The asphalt-rubber blend is held at 162°C (325°F) to 190°C (375°F) during the reaction period. The asphalt rubber may be allowed to cool to between 149°C (300°F) and 176°C (350°F). After the material has been reacted for a period of 30 to 60 minutes, the asphalt rubber can be metered into the HMA mixing facility or pumped into an agitated holding tank. The material is blended in 15,142-liter (4,000-gallon) batches. This system can produce approximately 15.2 to 31.2 metric tons (17 to 35 tons) of asphalt-rubber per hour, or sufficient binder to allow a contractor to produce approximately 226 to 454 metric tons (250 to 500 tons) of rubber-modified HMA per hour.

    California

      The asphalt-rubber HMA pavements built in California are similar to those built in Arizona. They use about 17 to 22 percent 600 181-m (30 mesh) CRM and require a reaction time of 30 to 60 minutes. Thus, there is a cross utilization of equipment and contractors between the two States.

      Manhole Adjusting Contractors, Inc., of Monterey Park has developed a rubber blending system where the asphalt-CRM is generally blended at the HMA plant. This process is similar to the original Arizona Refining Co. process. They use a combination of scrap tires and natural rubber (from ground tennis balls), ground rubber buffings, and 1 - to 6-percent asphalt modifier. The modifier is high resin, high flash point, aromatic hydrocarbon or extender oil. The rubber (1 part natural rubber and 3 parts rubber buffings) is fed into a mixing chamber where it is mixed at 90 gallons per minute. The mixing process is continuous. The asphalt cement and modifier are preblended and are between 190°C and 232°C (375°F and 450°F) when the CRM is added. The CRM is added using 27-kg (60-lb) bags. The asphalt-rubber mix is fed into a reaction trailer, where it is held a minimum of 30 minutes prior to use. After reaction the asphalt-rubber binder is fed into an agitated storage tank, where it is held until used. (See figure 6 for a photograph of the blending system.) The system produces sufficient asphalt-rubber binder to produce approximately 2,267 metric tons (2,500 tons) of HMA per day.

      Granite Construction, Inc., of Palm Desert operates the same system that FNF Construction in Phoenix does. It is also built by CEI Industries, Albuquerque, New Mexico.

    Florida

      Florida specifications call for either a 180 181-m or 425 181-m (80 mesh or 40 mesh) CRM at 5 and 12 percent concentration rates. With the smaller material and lower concentrations the "reaction" time can be shorter and is generally about 15 minutes. Thus, much of the equipment consists of a wetting chamber and a mixing chamber from which the material is pumped into a holding tank prior to being used in the HMA mixing facility. Anderson-Columbia Construction Co. in Lake City has established a terminal-type operation at their HMA plant site. It is shown schematically in figure 7. The CRM is delivered to the plant in bulk tanker trucks and then blown into one of two 71-metric-ton (80-ton) storage silos. The asphalt cement is metered into a 45;425-liter (12,000-gallon) blending tank equipped with two propellers. The ground tire rubber (GTR) is then weighed into the tank, where it is blended for a minimum of 15 minutes at about 1710C (3400F). The blended asphalt rubber is pumped into 22,712-liter (6,000-gallon) transport trucks for delivery to an HMA mixing plant. These trucks are equipped with heating systems and high viscosity pumps for circulation.

      HEATEC (a Division of Astec Industries) has built a trailer-mounted system. It is used by Martin Paving in Daytona Beach and by Bitcom in Coral Springs. The CRM is loaded into a crumb rubber hopper. (See figure 8 for a schematic.) It can be loaded from supersacks or from an auger. It is then augured into a 1,892-liter (500-gallon) prewet mixing tank. From there, the wetted material is pumped into another 1,892-liter (500-gallon) mixing tank for further blending. Heatec also manufactures a unit with one 3,028-liter (800-gallon) mixing tank rather than two 1,892-liter (500-gallon) tanks. From these mixing tanks, it is then pumped into an 11,356-liter (3,000-gallon) mixing tank where it is held until it is used The tanks are vertical with two mixing paddles, one near the bottom and one near the middle of the tanks. The asphalt cement is heated to 204°C to 232°C (400°F to 450°F) prior to mixing with the CRM. Care must be taken to make sure the final temperature of the blend (asphalt cement plus crumb rubber) is not exceeded.

      Blacklidge Emulsions has three different systems, one in Mobile, Alabama, one in Gulfport, Mississippi, and one in Tampa, Florida. The system in Tampa consists of two 26,497-liter (7,000-gallon) tanks that are trailer mounted. The tank is filled with asphalt cement, and then the CRM is weighed into the tank from a storage silo located on scales. The system in Mobile is a portable rig that was built as a coventure with Etinourer. This unit is fed from 22.6-kg (50-lb) sacks that are dumped into a hopper, and the CRM is augured into the blending unit.

      Rouse Rubber Industries, Inc., of Vicksburg, Mississippi, has developed a portable blending and metering unit mounted on a trailer. (See figure 9 for a photograph of the system and figure 10 for a schematic of the system. Note in the photo the bag delivery system.) In this system the rubber is augured into the primary tank, where it is mixed with an asphalt cement that is supplied at 162°C (325°F). A secondary tank is used to increase the reaction time for the process. The primary and secondary tanks are 1,892-liter (500-gallon) tanks with an active space of about 1,514 liters (400 gallons). The pump from the heat tank feeds the asphalt cement at a rate of 264 L/min (70 gal/mm). The percent rubber is controlled by adjusting the rate of the auger that feeds the rubber. The residence time for the asphalt-rubber blend in the mixing unit is approximately 15 minutes. The equipment can produce 22,704 liters (6,000 gallons) of reacted asphalt rubber in 1.5 hours.

    Summary

      Regardless of the type of blending operation used, the plant should be operated in such a way as to obtain a thorough and uniform mixture of the materials. This takes care and attention to details by the asphalt-rubber blender and the HMA contractor.

      When an extended delay (greater than 6 hours) occurs before the binder can be used after the reaction has been achieved, the asphalt-rubber mix is normally allowed to cool to 110°C to 121°C (225°F to 250°F). It can be reheated slowly prior to its use to a temperature of between 150°C (300°F) and 190°C (375°F). It must be thoroughly mixed before pumping and metering into the HMA plant. The viscosity of the asphalt-rubber binder should be checked. If it is out of the desired range, the asphalt-rubber blend is adjusted by the addition of asphalt cement and/or ground tire rubber to provide the proper viscosity. The effect of extended delays (i.e., prolonged storage at elevated temperature) on performance is not well documented. If the asphalt-rubber blender uses a bin-type feed system for the CRM, steps must be taken to ensure that the material is free flowing. As was discussed earlier with regard to shipping, the rubber can clump and the chunks can plug up the gates and auger systems used to feed the mixing operation. Possible remedies include a vibrator on the bin or an individual who periodically sticks the material in the bin to keep it free flowing.

    Operation of HMA Mixing Facility

      The operation of the HMA mixing facility for the construction of wet-processed asphalt-rubber HMA mixes is unchanged from that used for conventional mixes, with the exception that the mix is produced at higher temperatures. The blending equipment or agitated nurse tanks can easily be hooked up to both the drum and batch plants. When a drum plant is used, a two- or three-way valve is installed in the existing feed line on the output side of the asphalt pump. The asphalt-rubber metering equipment is then attached to the valve to feed the asphalt-rubber accurately. When a batch plant is used, the valve is installed directly onto the supply line leading to the weigh bucket. Many times a separate supply line to the weigh bucket is installed. Separate pumps are used by the blending contractor to prevent damage to the HMA contractor's pumps. The asphalt rubber is generally more viscous than the asphalt cement; thus, these pumps are generally larger than the standard pumps used on an HMA facility. Also, the pipes and supply lines need to be of sufficient diameter to allow the movement of a more viscous fluid. It may be necessary to employ jacketed and heated lines. There appears to be no problem with the asphalt-rubber material building up in lines or any requirements for unusual cleaning or flushing of equipment when asphalt-rubber HMA mixes are produced.

      The transportation of the asphalt-rubber HMA mix can be accomplished in any truck typically used for the transportation of conventional HMA. During the visits, there was no indication of sticking or other problems associated with the trucking. Wetting agents for the truck beds should be either soapy water or silicone emulsions. Solvent-based wetting agents should not be used.



    Placement / Handwork

      The handling and placement of the CRM-HMA mix must be accomplished to minimize segregation. It should be placed only when the surface temperature and weather conditions are optimum. Since the material is more viscous than conventional HMA, the temperature of the surface on which it is placed should be warm. Arizona DOT requires that the surface be at least 26°C (80°F). Even if the surface temperature requirement is met, it may be necessary to cease work due to existing or expected weather conditions that could have an adverse effect upon the CRM-HMA mix.

      The CRM-HMA mix delivered to the screed unit must be a free flowing, homogeneous mass in which there is no segregation, crusts, lumps, or migration of the asphalt rubber. It may be necessary to cover the hauling units with tarpaulins, and/or dump the material directly into the paver rather than using pick-up devices. Pick-up devices have been used; but because of the temperature sensitivity of the material, they should be used with caution. One contractor suggested that the screed unit may need to be heated periodically to prevent buildup of the mix on the screed. There can be pick-up of the HMA mix when the roadway is turned over to traffic. This can be addressed by lightly sanding the mix or by applying lime water to the surface.



    Compaction

      The viscosity and amount of asphalt binder in an HMA mix will affect the compactibility of the mix. The higher the viscosity of the binder, the stiffer the mix at a given temperature. Generally, the binder in an asphalt-rubber mix is stiffer than what the agency or the contractor is accustomed to. Asphalt-rubber mixes must be compacted while they are hot. Compaction is generally not a problem if the temperature is maintained. The criticality of the temperature increases as the rubber content increases. Arizona DOT requires that the temperature of the rubber-modified HMA be at least 135°C (275°F) just prior to compaction and that compaction be completed prior to the mix temperature reaching 104°C (220°F). A cautionary note: The presence of CRM may generate fumes and smoke at typical compaction temperatures.

      The compaction can be accomplished with either vibratory or steel-wheel rollers. Pneumatic rollers should not be used, as the rubber-modified binder can pick up on the pneumatic wheels.

    Costs of CRM Binder / Mix

      price of CRM asphalt cement and HMA varies from region to region. It will generally consist of the cost of the CRM material, the asphalt cement, and the costs of blending the material. As the CRM material is ground finer, the cost of the CRM will increase; and as the percentage of CRM in the asphalt cement increases, the cost of the asphalt-rubber binder will increase.

      A survey of the suppliers of CRM material indicates that the approximate cost of the CRM at the CRM supplier's grinding plant varies with particle size. Typical costs are shown in table 7. Table 8 presents the typical cost of asphalt cement and asphalt rubber for each of the surveyed States. The prices described in table 8 reflect the reduction in the cost of asphalt-rubber binder since the patents expired. In Arizona in 1991 (the year before the patents expired), the average bid price was $400 per metric ton ($448 per ton). Florida reports that the cost of blending, etc., by the asphalt-rubber supplier is approximately $4.50 per tonne ($5.00 per ton).

      Table 9 presents the cost of the various asphalt-rubber mixes used in each of the three surveyed States. The cost figures presented in table 9 should be used only as a guide for large quantities of asphalt-rubber binder. On projects that contain small amounts of asphalt-rubber binder (which reflects many of the projects being built), the prices can, and will, probably be considerably higher due to the cost of mobilization of the blending equipment. Also, it should be noted that the potential decrease in cost of CRM-HMA due to the use of thinner sections has not yet been addressed.

    Summary

      This chapter presented procedures used to blend the CRM with the asphalt, as well as mixing and placement procedures. Also presented are typical costs for the CRM, the asphalt-rubber binder, and the finished mix.




    Table of Contents | Chapter 1 | Chapter 2 | Chapter 3
    Chapter 4 | Chapter 5 | Chapter 6 | Chapter 7 | Glossary

    CRM Suppliers | CRM Blenders | Typical Specifications
    Local Specifications | References

    Membership Newsletters
    Contact FAQ Library
    Links Home Page Events
    [home library membership newsletter FAQ links contact events]