This section presents the background on LCCA
and describes the process currently being used by the Federal
Highway Administration.
Background
Agencies have historically used some form of life cycle cost
analysis (LCCA) to assist in the evaluation of alternative pavement
design strategies. For example, the 1986 AASHTO Guide for the
Design of Pavement Structures, the use of LCCA was encouraged
and a process laid out to evaluate the cost effectiveness of
alternative designs (4). However,
until the National Highway System (NHS) Designation Act of 1995,
which specifically required agencies to conduct LCCA on NHS projects
costing $25 million or more, the process was only used routinely
by a few agencies (5). The implementing
guidance did not recommend specific LCCA procedures, but rather
specified the use of good practice.
The FHWA position on LCCA is defined in its
Final Policy Statement published in the September 18, 1996, Federal
Register (5). FHWA policy indicates
that LCCA is a decision support tool. As a result, FHWA encourages
the use of LCCA in analyzing all investment decisions.
Although the Transportation Equity Act for
the 21st Century (TEA-21) has removed the requirement for agencies
to conduct LCCA on high cost projects, it is still the intent
of FHWA to encourage the use of LCCA for NHS projects. As a result,
FHWA has developed a training course titled "Life Cycle
Cost Analysis in Pavement Design" (Demo Project 115) to
train agencies in the importance and use of sound procedures
to aid in the selection of alternate designs or rehabilitation
strategies (6).
LCCA process
LCCA should be conducted as early in the project development
cycle as possible. The level of detail in the analysis should
be consistent with the level of investment. Basically, the process
involves the following steps:
1) Develop rehabilitation and maintenance strategies for the
analysis period
2) Establish the timing (or expected life) of various rehabilitation
and maintenance strategies
3) Estimate the agency costs for construction, rehabilitation,
and maintenance
4) Estimate user and non-user costs
5) Develop expenditure streams
6) Compute the present value
7) Analyze the results using either a deterministic or probabilistic
approach
8) Reevaluate strategies and develop new ones as needed
The application of these steps to the present study are described
below.
Establish alternative design strategies
The primary purpose of a LCCA is to quantify the long-term economic
implications of initial pavement decisions. Various rehabilitation
and maintenance strategies can be employed over the analysis
period (Figure 1a). This first step is to identify alternate
strategies over the analysis period, typically 40 years. Alternate
design strategies used in Arizona and California for asphalt
pavement were obtained through personal interviews. Typical strategies
used in these states are summarized in Table 1. For each of the
scenarios considered, there is a logical comparison between conventional
mixtures and mixtures containing asphalt rubber. The pavement
alternates receive different maintenance (or rehabilitation)
treatments until the life reaches the analysis period of 40 years
(see Figure 1b).
Determine expected life of rehabilitation
and maintenance strategies
The next step was to obtain estimates of expected lives for the
various rehabilitation and maintenance strategies (7).
This was also determined based on interviews with state and local
agencies in each state. Estimates for pavement life for each
of the scenarios considered by the local agencies are given in
Tables 2 and 3. Similar data was collected for the state highway
agencies surveyed in Arizona and California (7).
The table includes an average life, the lowest and highest expected
life for a given strategy. The low and high values represent
the 10 and 90 percentile values for expected life. It should
be emphasized that the estimated lives are best estimates only
and in many cases the AR alternatives have not yet reached the
90% value.

a) Analysis period for a pavement design alternative
Back To Scenarios
Back To Scenarios
Estimate agency costs
Agency costs include all costs incurred directly by the agency
over the life of the project. These costs typically include expenditures
for preliminary engineering, contract administration, construction,
including construction supervision, and all future maintenance
(routine and preventive), resurfacing and rehabilitation. Estimates
for these costs were obtained from Arizona and California and
these are also summarized in Tables 2 and 3 (7).
The low and high values represent the 10 and 90 percentile values
for expected costs.
Salvage value represents the value of an investment alternative
at the end of the analysis period. The method used to account
for salvage value was prorated-based on the cost of final rehabilitation
activity, expected life of rehabilitation, and time since last
rehabilitation activity as shown below:
(1)
Back To Scenarios
Estimate user and non-user costs
In simple terms, user costs are those incurred by the highway
user over the life of the project. They include vehicle operating
costs (VOC), user delay costs, and accident costs. For most pavements
on the national Highway System (NHS), the VOC are considered
to be similar for the different alternatives. However, slight
differences in VOC rates caused by differences in roughness could
result in huge differences in VOC over the life of the pavement.
For purposes of this paper, VOC rates are assumed to be equal.
Delay cost rates have been derived for both passenger cars
and trucks. These can range from $10-$13/veh-hr for passenger
cars and $17-$24/veh-hr for trucks (5).
Because these costs require project specific information for
inclusion in LCCA and the value of delay costs is often questioned,
the authors opted to use a simpler approach using lane rental
fees. Typical values for lane rental fees might vary with traffic
volume as follows (7):
|
Type of Facility |
|
$/Lane-Mile/Day |
|
Low volume |
|
1,000 |
|
Moderate volume |
|
5,000 |
|
High volume |
|
10,000 |
These values are estimates only, but allow the effect of delays
to be accounted for indirectly.
Accident and non-user costs may also vary with type of rehabilitation
and maintenance strategy. For purposes of this paper, the effect
of pavement strategy on these costs were ignored.
Develop Expenditure Streams
Expenditure streams are graphical or tabular representations
of expenditures over time. They are generally developed for each
pavement design strategy to visualize the extent and timing of
expenditures. Figure 2 is an example of an expenditure stream.
Normally, costs are depicted as upward arrows and benefits are
reported as negative cost (or downward arrows). The only benefits,
or negative cost, included herein are the costs associated with
the salvage value.
Figure 2. Typical expenditure stream diagram for a pavement design
alternative
Compute net present value (NPV)
LCCA is a form of economic analysis used to evaluate the cost
efficiency of various investment options. Once all costs and
their timing have been established, the future costs must be
discounted to the base year and added to the initial cost to
determine net present value (NPV). NPV is calculated as follows:
(2)
Both agency and user cost are incorporated into the analysis.
The results can be presented using a deterministic or probabilistic
approach as will be discussed in the examples to follow.
Analyze results
Once completed, all LCCA results should be subjected to a sensitivity
analysis to determine the influence of major input variables.
Many times the sensitivity analysis will focus on inputs with
the highest degree of uncertainty (i.e., life) in an attempt
to bracket outcomes. For example, if a conventional project lasts
10 years, how long must an asphalt rubber design last for it
to be cost effective?
Reevaluate design strategy
Once the NPV has been computed for each alternative, the analyst
needs to reevaluate competing design strategies. Questions to
be considered include:
- 1) Are the design lives and maintenance and rehabilitation
costs appropriate?
- 2) Have all the costs been considered (e.g., shoulder and
guard rail)?
- 3) Has uncertainty been adequately treated?
- 4) Are there other alternates which should be considered?
Many assumptions, estimates, and projections feed the LCCA
process. The variability associated with these inputs can have
a major influence on the results.
|