 |

The life cycle cost analysis calculations presented herein
were completed using a combination of two widely available software
programs, MicroSoft Excel (deterministic) and Palisade's @Risk
(probabilistic) as suggested by the Federal Highway Administration
(5). This combination allows both
the deterministic and probabilistic approaches to be analyzed.
Before describing the scenarios investigated, an overview of
the general features of each is described along with the assumptions.
Scenario overview
- Several features were common to each analysis. These are
described below:
- A 40-year analysis period was selected based on FHWA recommendations
(5).
- Each major rehabilitation activity triggered a lane rental
cost calculated as a function of the production rate assumed
for that traffic level/facility type.
- Routine (preventive) maintenance may be applied between major
rehabilitation activities depending on the agency.
- Salvage values were calculated as a prorated percentage of
the expected life of the rehabilitation.
- All costs were converted to present worth terms to compare
asphalt rubber and non-asphalt rubber alternatives.
In addition, several assumptions and simplifications were
necessary. These are listed below:
- 1) Maintenance was applied as indicated by the agency. Once
triggered, maintenance costs occur until the next major rehabilitation
activity.
- 2) User delay costs were approximated using the lane rental
costs. The authors recognize that more accurate costs could be
determined if actual average daily traffic (ADT) were known and
delays were computed; however, this was beyond the scope of this
project.
Several input were consistent among all different scenarios.
These included:
*Four percent was used for all deterministic runs;
when variability was considered either 2.5, 4.0, or 5.5 was used
for a given calculation.
| Variable |
|
Input Values |
| Discount rate, % |
|
2.5, 4.0, 5.5 |
| Analysis period, yrs |
|
40 |
| Lane rental costs, $/lane-mile/day |
|
1,000; 5,000; 10,000
representing low, medium, and high traffic levels, respectively |
Project length, mi
+ City/county projects
+ State DOT projects |
|
5
10 |
| Production rates, lane-miles/day |
|
|
+ City/county projects
+ State DOT projects |
|
2
3 |
The maintenance and rehabilitation strategies used as well
as the expected lives and costs varied as described below.
Scenarios investigated
The scenarios investigated were presented in Table
1. For each agency, several rehabilitation and maintenance
strategies were evaluated. The expected lives and costs for all
rehabilitation and maintenance strategies used in the analysis
are given in Tables 2
and 3.
Results
In the deterministic approach, variability of the inputs
is not considered. For the scenarios evaluated, the net present
worth values are summarized in Tables 4-6. It should be noted
net savings result from the use of AR in most cases for the inputs
used in the analysis as indicated by ratio of costs > 1.0.
For those situations where the asphalt rubber alternate was
not cost effective (e.g., ratios < 1.0), the following were
determined:
- 1) Maricopa County (Alternate B vs D). For the asphalt
rubber to be cost effective, the average expected life would
have to be 11 years (instead of 10) to yield a ratio > 1.0.
- 2) City of Mission Viejo (Alternate K vs L). The estimated
life of the AR alternate must be increased by 1 year (from 20
to 21) for the AR alternate to be cost effective.
It should be emphasized that all of the estimated lives are
best estimates provided by the agencies. Any change in estimated
life can have a significant effect on the LCCA.
For the probabilistic analysis, the input variables were selected
randomly within the ranges given for all inputs except the following:
- Analysis period, fixed at 40 years
- Lane rental costs, fixed as determined by traffic level
- Project length, fixed as determined by traffic level
- Production rates, fixed as determined by traffic level
Figure 3 illustrates the approach
used and the interpretation of the results of these calculations
are shown schematically in Figure
4. In this example, alternate A would be more cost effective
77 (100 - 23) percent of the time.
Figure 5 provides
the results for the City of Phoenix. If the percentile where
the costs for each alternate within a scenario are equal (0 savings)
is determined, then the data in Figure
5 suggests that asphalt rubber is more cost effective than
the conventional alternative in many applications considered
(see Table 7). As shown
in Table 7, the following
observations are made:
- 1) City of Phoenix. The results indicate the AR alternate
to be cost effective in all applications except when comparing
alternates A vs C (high and low traffic). These results indicate
it is more cost effective to use microsurfacings or slurry seals
prior to placing the AR overlay. Deferring major rehabilitation
to later will always be more cost effective.


|