|
![]()
The concrete pavement began to fail in 1974, just five years after construction. The failure began as large corner cracks and progressed to transverse cracks and severe spalling at the transverse joints. Maintenance sealed the cracks and patched spalls as best as possible and in the process expended considerable funds averaging over $80,000 per year. As the pavement deteriorated the cracking continued to increase. From 1980 to 1989 the percent cracking increased from one percent to nine percent (Figure 1). The ride quality also suffered, even though maintenance repaired the worst locations. In 1980 the ride was 1500mm/km (100 inches/mile) and by 1989 it had increased to 1980mm/km (132 inches/mile). A value of 2220mm/km (148 inches/mile) is considered objectionable. Twenty percent of the project miles exceeded the objectionable ride level before overlaying. In general the performance of the concrete pavement was very poor. In addition the traffic loadings over the course of time increased dramatically. In 1969 the annual 80kn (18 kip equivalent single axle loads (ESAL's)) was about 120,000. In 1990 it was 1,600,000 and by 1999 it is presently 2,500,000 which is about 21 times as great as 1969. Design began in 1988 and reconstruction was very strongly
considered. The adjacent 6.7km (four mile) section of I-40 (MP
191-195) had experienced the same type and degree of failure
and had been reconstructed. The reconstruction (2) involved the
building of detours and closing the interstate in one direction
for one year. Thus two reconstruction projects were built over
a two year period in the years of 1985 and 1986. The reconstructed
sections were composed of 200-275mm (8-11 inches) of HMA on top
of 150mm (6 inches) of permeable asphalt bound base and 100-175mm
(5-7 inches) of drainable aggregate base. The pavement structural
section was placed on top of a geotextile separation fabric to
keep the wet clay from pumping into the aggregate base. A complete
edge drain system with slotted pipe was also installed. The total
cost of construction of the two projects was about $15 million.
In order to reconstruct the Flagstaff I-40 (MP 195-205) project
it would have been necessary to build the project in four phases,
since detours of more that 8.3km (five miles) were not allowed.
In addition the construction would have taken four years to complete,
however it was strongly questioned whether maintenance could
maintain the pavement for that long, given its very poor condition
(Figure 1). The overall cost of reconstruction was estimated
to be at least $30 million. It was finally concluded that the
project could not be reconstructed. In addition, due to money
and time constraints the project would have to be overlaid within
a tight budget and work completed in one construction season
of about six months. Various overlay strategies were considered
including many different overlay thicknesses, use of a fabric
interlayer, asphalt rubber interlayer, various mixes, edge drains
and cracking and seating. Each alternative was discussed and
reviewed at both the central office and the district office.
In addition the project was also selected (3) as a Strategic
Highway Research Project (SHRP) Specific Pavement Studies (SPS-6)
to test various overlay and rehabilitation strategies on concrete
pavement. With an asphalt rubber binder the selected project
design strategy represented a test of whether a relatively thin
pavement overlay could control reflective cracking. Although
the design was for ten years virtually everyone involved in the
project considered this to be at best a six year design given
the thin overlay design section and the very poor condition of
the concrete. After much internal discussion and debate the final
pavement design section included edge drains, crack and seat
of the concrete pavement, a 125mm (five inch) overlay composed
of a 75mm (3 inch) conventional dense hot mix asphalt (HMA) and
50mm (2 inch gap graded) asphalt rubber mix (AR-AC). An The overlay thickness and layer placement was discussed right up to the final days before the bid advertisement. The discussion centered around whether the AR-AC or the HMA should be placed directly on top of the broken concrete. Previous experience with asphalt rubber interlayers indicated that the AR-AC should be placed on top of the cracked surface before overlay. The other position of placing the AC on top of the broken concrete seemed more in keeping with its role as a leveling and structural layer which would probably crack very soon after construction (first winter). The top overlay of AR-AC and AR-OGFC would then perform not only as the leveling and structural layer but also as the final flexible layer capable of resisting reflection cracking. The project was designed in this manner, however, a test section was built with the 50mm (two inch) AR-AC on top of the broken concrete pavement and a 50mm (two inch) HMA placed on top as the final overlay. The use of the AR-OGFC as the final wearing course had been previously tried on a concrete pavement in Tucson, Arizona. Its performance in Tucson on Interstate 19 has been very good and it was always considered as the most appropriate wearing course. Typically in 1990 OGFC's in Arizona were placed with conventional AC-20 (PG-64-16) at a six percent maximum binder content which is normally the maximum the rock can hold before an excess drains off. Asphalt rubber is over ten times more viscous than AC-20 (PG-64-16) at hot mixing temperatures of 177°C (350°F) and thus can be applied to an OGFC rock gradation at a rate of nine to ten percent by weight of the mix. This extra coating thickness increases durability and slows down aging. In addition the thick rubbery coating helps to retard reflection cracking. In addition to the material related design issues, constructability
issues were addressed in the design by meeting with district
construction personnel. It was agreed early on that the project
construction phasing should be such that the project could be
completed in one summer paving season. To do this the specifications
required the contractor to begin with the edge drain. After sufficient
edge drain was completed the crack and seat would start. Crack
and seat operations had to be done at night to avoid interfering
with the edge drain installation and to be in sync with the overlay
operation. The crack and seat drop height and spacing was checked
by deflection testing and cores to verify the quality of the
work. In addition an incentive of $15,000 per day to finish paving
the overlay ahead of schedule was included. The maximum incentive
was set at $450,000 with a due date of October 1, 1990. With
all the numerous design issues described in plans and special
provision specifications the project was bid in April, 1990.
|